Thompson School District Bond Projects

Centennial

Front of Centennial Elementary School

Original Construction Date: 1976

Project Updates

graph showing percent encumbered

Total Budget

$1,280,800

Contracted to Date

$1,231,100

Last Updated: 05/04/2023

Status Bond Project Year Scheduled Year Completed
Security Upgrades 2022 2020
Asbestos Abatement and Inspection 2022 2022
Playground Safety Improvements 2022 2019
Roof Repair / Replacement 2022 2019
High Impact Building Improvements 2022 2022