Lincoln
Project Updates
Total Budget
$1,239,400
Contracted to Date
$1,203,900
Last Updated: 02/13/2023
Status | Bond Project | Year Scheduled | Year Completed |
---|---|---|---|
✓ | Security Upgrades | 2021 | 2020 |
✓ | Asbestos Abatement and Inspection | 2021 | 2021 |
✓ | Roof Repair / Replacement | 2021 | 2021 |
✓ | Fire System Upgrade | 2021 | 2020 |
✓ | Playpad Asphalt Repair and Replacement | 2021 | 2020 |
✓ | High Impact Building Improvements | 2021 | 2021 |