graph showing percent encumbered

Total Budget

$1,671,100

Contracted to Date

$1,657,400

Last Updated: 02/13/2023

Status Bond Project Year Scheduled Year Completed
Security Upgrades 2022 2020
Asbestos Abatement and Inspection 2022 2022
Fire System Upgrade 2022 2021
Roof Repair / Replacement 2022 2020
Boiler Replacement and Improvements 2022 2022
High Impact Building Improvements 2022 2022