Skip To Main Content
Thompson School District Bond Projects

Truscott

Front of Truscott Elementary School

Original Construction Date: 1969

Project Updates

graph showing percent encumbered

Total Budget

$1,655,049

Contracted to Date

$1,655,049

Last Updated: 10/28/2024

Status Bond Project Year Scheduled Year Completed
Security Upgrades 2022 2020
Asbestos Abatement and Inspection 2022 2022
Fire System Upgrade 2022 2021
Roof Repair / Replacement 2022 2020
Boiler Replacement and Improvements 2022 2022
High Impact Building Improvements 2022 2022