Thompson School District Bond Projects

Thompson Valley

Picture of main entry from the street

Updated Main Entry!

Project Updates

graph showing percent contracted

Total Budget

$9,512,323

Contracted to Date

$9,512,323

Last Updated: 10/28/2024

Status Bond Project Year Scheduled Year Completed
Security Upgrades 2021 2021
Asbestos Abatement and Inspection 2021 2021
Ventilation System Improvements 2021 2022
Parking Lot Repair and Replacement 2021 2021
Irrigation Repairs and Replacement 2021 2022
High Impact Building Improvements 2021 2021