Walt Clark

Walt Clark Middle School

Original Construction Date: 1978

Project Updates

graph showing percent contracted

Total Budget

$3,468,000

Contracted to Date

$3,452,000

Last Updated: 02/16/2023

Status Bond Project Year Scheduled Year Completed
Security Upgrades 2021 2021
Asbestos Abatement and Inspection 2021 2021
Boiler Replacement 2021 2021
Roof Repair / Replacement 2021 2021
Asphalt Repair and Replacement 2021 2021
High Impact Building Improvements 2021 2021